SAMSUNG SEH
Investor:
Client:
Location:
In cooperation with:
Samsung Electronics Magyar Zrt.
Samsung Electronics Magyar Zrt.
Jászfényszaru l Hungary
Samsung C&T, Hanmi Global
Phase: V1
Description: CRT TV assembly
Total floor area: 14,000 m2
TECTON’s role: General designer
Year of completion: 2001
Phase: V2 LCM
Description: LCM prodcution in clean room
Total floor area: 6,000 m2
TECTON’s role: Design-build
Year of completion: 2011-2012
Phase: V3 Extension
Description: SMT extension
Total floor area: 3,600 m2
TECTON’s role: Design-build
Year of completion: 2017
Phase: V2 MiniLED
Description: Building reconstruction for MiniLED technology
Total floor area: 2,000 m2
TECTON’s role: Design-build
Year of completion: 2022
Phase: V2
Description: TV assembly extension
Total floor area: 23,000 m2
TECTON’s role: General designer
Year of completion: 2008
Phase: V3
Description: SMT extension in new building
Total floor area: 22,000 m2
TECTON’s role: General designer
Year of completion: 2013
Phase: V1 Clean Area
Description: Conversion of storage to clean production area
Total floor area: 1,000 m2
TECTON’s role: Design-build
Year of completion: 2022